Project Details
Description
A physical model test is planned for the determination of the conversion and extension measures for the Gstins dam, which is to be reproduced as a sectional model on a model scale suitable for the purpose of the investigation. The main aim of the investigation is to prove the conveying capacity of the weir spillway and sufficient energy conversion in the stilling basin and to determine the necessary expansion measures for the weir facilities.
Status | Finished |
---|---|
Effective start/end date | 12/06/13 → 30/03/14 |
Fingerprint
Explore the research topics touched on by this project. These labels are generated based on the underlying awards/grants. Together they form a unique fingerprint.